Building the Building
Architect's drawing of our new location, completed in the Fall 2002.
Time Line
| September, 2002 | |
![]() |
![]() |
| Moving the boulder. Our new sign. | |
| Opening Day, August 19, 2002 | |
![]() |
![]() |
| Dan Hoffman, Jim Shutter, Gene Brennan, and our first line of customers | |
| August 2002 | |
![]() |
![]() |
| View from Seneca Street, Lazure painted walls. | |
| July 2002 | |
![]() |
![]() |
| View from Seneca Street as the brick goes up | |
| June 2002 | |
![]() |
![]() |
| Bricks before and after | |
| May 2002 | |
![]() |
![]() |
| Views from State Street and Seneca Street | |
| April 2002 | |
![]() |
![]() |
| Wrapped in Tyvek, the staff visits the site | |
| March 2002 | |
![]() |
![]() |
| Bill Myers, CEO, describes the plans to staff | |
| February 2002 | |
![]() |
![]() |
| Signing of the Beams | |
| January 2002 | |
![]() |
![]() |
| The look of the building emerges, with the roof sheeted and tar papered, and the arch defined. |
|
![]() |
![]() |
| The roof trusses go on. | |
| December 2001 | |
>![]() |
![]() |
![]() |
<![]() |
| The building takes shape as the steel structure goes up. | |
| November 2001 | |
![]() |
![]() |
| Pouring the concrete into the waffle foundation. | |
| October 2001
|
|
![]() Preparing for the waffle foundation. |
|
| November 2000
|
What's that big hole? Environmental remediation. |
| September 2000
|
Nothing but rubble. |
| July 2000
|
|
| IMG SRC="img/bldg6.jpg" WIDTH=175 HEIGHT=131 ALT="June 28,2000" BORDER=0 |
|
| Demolition begins 06/28/00 at the corner of Fulton and Seneca Streets. |
|
![]() 6/29/00 |
![]() |
| March 2000
|
The building site is being readied for the upcoming demolition work. Bids are being accepted for asbestos remediation and demolition. Groundbreaking is tentatively |